The following is an email I received today concerning the new CRMP EIS. No doubt many of you did as well. I have posted it for those who aren't on the Eternal Waiting List.
Dear _______________________,
The Final Environmental Impact
Statement (EIS) to revise the Colorado River Management Plan (CRMP) was released
today, 11/10/05. It can be downloaded or viewed through our website
at: http://www.nps.gov/grca/crmp.
Included in this document is the NPS
preferred option to replace the current waitlist system for issuing
noncommercial permits with a “hybrid” weighted lottery system. The document
also explains the NPS preferred option for transitioning from the current
waitlist system to the new hybrid weighted lottery system. For your convenience
we are including key excerpts from each of those sections here. The preferred
alternative also would add many additional noncommercial launch opportunities
each year: 56 additional trips in the May – August time period, 101 additional
trips in the shoulder season (March, April, September, and October), and 92
additional trips in the November – February time period.
Key EIS text regarding the hybrid
weighted lottery:
The
hybrid weighted lottery option is a combination of
several elements of the permit system options listed above and responds to the
public’s suggestions during public scoping. Once each year, a
lottery would be used to award the
following year’s noncommercial launches. Lottery applications would list
the applicant and all potential alternate trip leaders (“potential leaders”) and could
include up to five launch dates throughout the year for initial consideration.
Each applicant’s chance in that year’s lottery would vary depending on the
minimum number of years it would have been since any potential leader had won
through the lottery or participated in any part of a Lees
Ferry to Diamond
Creek river trip. For example, based on
the most recent time any potential leader had been on a commercial or
noncommercial river trip, the application would receive the following number of
chances in the lottery to obtain a river permit:
5 or more calendar years before
launch date = 5
chances
4
calendar years before launch date = 4
chances
3
calendar years before launch date = 3
chances
2
calendar years before launch date = 2
chances
1
calendar year before launch date = 1
chance
Individuals could
be listed as potential leaders on only 1 application per year and must be 18
years old by the requested launch date. Once a river permit had been awarded,
deposits would be charged immediately and would become nonrefundable. Deferments
and/or swapping of permits would not be allowed. Trips could
be passed to any of the potential leaders listed on the
lottery application, and trip
leaders
would continue to have the freedom to change their list of participants up to
within three weeks of launch.
As
any unclaimed or cancelled permits become available, they would be
awarded through subsequent lottery drawings. Thus, applications
could include more than the five launch dates initially considered. Applicants
would be prompted to indicate on their applications the latest date they would
be willing to accept a specific launch date should it become available due to
cancellations. For example, an applicant would be asked on their application if
they would be willing to accept a river trip if it suddenly became available 10
days before the launch is scheduled.
Permits that
continue to be unclaimed through the lottery 30 days before the launch would
be posted on the internet and awarded on a first-apply, first serve
basis.
Key EIS text regarding transitioning
from the waitlist system to the hybrid weighted lottery permit
system:
Under this
option, three stages of expedited transition would take place during the first
four to six months after the Record of Decision (ROD) is
signed.
Stage
1 would be first stage of transitioning from the current
waitlist to
the new permit system. In this stage, members of the
waitlist would be given one final two-month chance to schedule launch dates
through the existing waitlist. A total of 600 launch dates (from the 2007
through 2011 seasons) would be made available for this purpose. All those people
who do not succeed in this stage would then transition to stage 2.
Stage
2 would be the modified waitlist stage, in which existing waitlist
rules would be changed to allow waitlist members to band together and advance up
the list based on their combined waits. For example, if Tom had been on the
waitlist for five years and Robin for nine years, their combined wait would be
14 years, so they would receive one number and be ahead of all those who had
waited 13 years or less. After a two-month period, where members would be
allowed to join together, 600 additional launch dates (from the 2007 through
2011 seasons) would be made available to those combined waitlist members with
the greatest wait totals. All those who had not succeeded in this stage would
then move onto stage 3.
Stage
3 would be the final transition stage. Everyone would need to
give up their old waitlist spot and the existing waitlist
would no longer exist. In exchange for individual waitlist members giving up
their spots, each waitlist member would have their choice of the following two
basic options:
· One option would consist of
individuals on the waitlist trading their spot on the
waitlist for one extra chance, in addition to the total chances they would
normally have had, in the new hybrid lottery for each year they had been on
the existing waitlist. These extra chances would expire only upon being awarded
a trip or through participation in nay other trip (noncommercial or commercial).
These extra chances would greatly improve each person’s chances in the
lottery.
· The other option would be for an
individual to accept a refund for the price they paid to join and leave the
waitlist.
This
three-stage expedited transition process would transition all members off the
waitlist within 6 months. The Park expects
the majority of stage 1 launch dates will go to people at the very top of the
waitlist. In addition, the Park assumes that an average of 3 people will join
together to claim each stage 2 launch. Together this would allow 33% (2,400
people) to have gained a launch date through this point in the transition. The
10-year chances for the remaining 4,300 former waitlist members could be
calculated as follows: If all 4,300 apply each year and are part of an assumed
7,000 total lottery applications received each year,
the Park predicts that over half of these people will have received a launch
date within ten years. The Park also predicts that in twenty years, no more than
561 of these people will continue to have been unsuccessful in obtaining a
launch date. Therefore, this three-stage expedited transition process, coupled
with the new permit system, should result in a much improved
success rate for the majority of those who are currently on the waitlist.
Because of these pending changes,
the current “Continuing Interest” (CI) requirement has been waived for this
winter, and the “Initial Scheduling” process has been postponed until
February
1st, 2006:
- CI forms are not due for the winter
of 2005-2006. Typically at this time of year all people on the Noncommercial
River Permit Waitlist are required to express in writing their “Continuing
Interest” in remaining on the waitlist for the following April 16 through April
15 time period. Since the NPS preferred option in the EIS calls for a rapid
transition away from the waitlist, we see no point in requiring CI forms this
year. However, if you’ve moved in the last year or changed your contact
information, please fax or mail your updated information to the River Office.
- Initial Scheduling is being
postponed until February 1st, 2006. Typically at this time of year
the River Permits Office would initiate the annual “Initial Scheduling”
opportunity and make available 250 or so launch dates from the 2007
noncommercial year. Due to the release of the EIS and the desire to expedite
the transition process, this year’s “Initial Scheduling” opportunity is being
postponed until February 1st, 2006. Under the proposed transition
option, a total of 600 launch dates from the 2007 through 2011 calendar years
would be made available through the normal initial scheduling process for those
on the waitlist. This would be considered Stage 1 of the transition, the last
chance for people to schedule launch dates through the waitlist as we all know
it. Transition Stage 2 as described above would commence once Stage 1 is
completed (approximately 2 months later) and include an additional 600 launch
dates. Finally, we would hope to release the remaining launch dates for 2007
through the lottery as early as mid-summer, 2006. All together this should
result in close to 1500 launch opportunities being scheduled through the River
Office over the next 10 months!
Other news:
- Separate from the EIS, the River
Permits Office has received approval to replace our system of using Social
Security Numbers to track users with one that uses names, addresses, and
birthdates.
- Because noncommercial and commercial
launch dates for 2006 were previously scheduled, 2006 will be considered a
transition year. This means that we will not implement the new launch schedule
until 2007. However, we will be reviewing the existing 2006 launch patterns
closely and determining whether we can add any additional noncommercial launch
opportunities within 2006 (for Carrying Capacity Standards see EIS Chapter 2,
page 32).
- Currently scheduled trips will no
longer have the option to postpone their launches to 3 years into the future
(“trip deferments”). This is essential for ensuring the new launch schedule can
be followed. Trip leaders, however, will have a new option: they will be able
to list additional potential alternate trip leaders. The EIS allows anyone who
has not been on the river the same year to be qualified to go on a trip. Those
with scheduled trips will therefore be given the opportunity to list additional
people as potential alternate trip leaders. This will provide an opportunity
for these trips to continue as planned with or without the original trip
leader.